New Contracts for Works

Contracts were signed today in the business premises of the FBH Roads.

New Contracts for Works

Under the FBIH Roads Floods Repairs and Upgrade Project, following contracts for works have been signed:

  • Lot 1 – Rehabilitation of tunnel Čaklovići, M4 - Simin Han – Donje Caparde

The Contractor is Hering d.d. Široki Brijeg and the contract amount is BAM 2.857.873,06 (with VAT included).  Contract period is five months.

  • Lot 2 – Construction of Baypass I Phase, Donji Vakuf M5

The Contractor is JV Bossil d.o.o. Vitez and Pont d.o.o. Sarajevo. Contract period is 12 months and the contract amount is BAM 3.954.684,91 (with VAT included).

The contracts will be financed by the EBRD credit funds.

JP Ceste FBiH d.o.o. Sarajevo