New contracts under the Roads Floods Repairs and Upgrade Project

As part of the FBIH Roads Floods Repairs and Upgrade Project, the representatives of the contractors and Ljubo Pravdić, director of the PC Roads of the FBH have signed contracts for the following works:

New contracts under the Roads Floods Repairs and Upgrade Project
  • M1.8 Border BH/HR – Lončari and Pelagićevo –Srebrenik Road Reconstruction.
    The contractor is JV Jata Group d.o.o. and Roading d.o.o Srebrenik and the contract amount is BAM 6.359.913,59 with VAT included.
  • M1.8 - Srebrenik – Šički Brod Road Reconstruction.
    The contractor is JV Jata Group d.o.o. and Roading d.o.o Srebrenik and the contract amount is BAM 6.171.667,08 with VAT included.
  • M15 - Kamičak – Ključ Reconstruction following road movement: Crljeni – Zgon and M15 Kamičak – Ključ Bridge Reconstruction across r. Banjica.
    The contractor is HP Investing d.o.o. Mostar and the contract amount is BAM 5.395.359,02 with VAT included.
  • M5 - Kaonik – Gromiljak Completion of reconstruction of Busovača – Draga, Delfine krivine and Jehovac – Brestovsko.
    The contractor is Strabag AG Austria and the contract amount is BAM 4.062.281,04 with VAT included.
  • M16.2 - Prozor – Jablanica 1 Rehabilitation of Tunnel Jasen.
    The contractor is JV HP Investing d.o.o. Mostar and Euro-Asfalt d.o.o. Sarajevo and the contract amount is BAM 5.516.867,61 with VAT included.

Total value of the above contracts inclusive of VAT is BAM 27.506.088,30.

All contracts will be financed by the EBRD credit funds.